PMI Certified Associate in Project Management (CAPM) CAPM Question # 119 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 119 Topic 12 Discussion

CAPM Exam Topic 12 Question 119 Discussion:
Question #: 119
Topic #: 12

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?


A.

Monitor project stakeholder relationships using engaging strategies and plans


B.

Send all project documents to stakeholders each time they are modified


C.

Schedule monthly meetings with the stakeholders, including team members


D.

Engage only with the project sponsors


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.