PMI Certified Associate in Project Management (CAPM) CAPM Question # 118 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 118 Topic 12 Discussion

CAPM Exam Topic 12 Question 118 Discussion:
Question #: 118
Topic #: 12

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?


A.

Project activities


B.

Work packages


C.

Planning packages


D.

Project deliverables


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.