Based on the principles of Earned Value Management (EVM) found in the PMBOK® Guide, the Cost Variance (CV) is a measure of cost performance on a project.
Formula: $CV = EV - AC$
Calculation: Given the metrics:
Earned Value ($EV$) = $\$20,000$
Actual Cost ($AC$) = $\$22,000$
$CV = 20,000 - 22,000 = -2,000$
Interpretation:
A negative CV ($-2,000$ in this case) indicates that the project is over budget. It means the actual cost spent to date is higher than the value of the work performed.
A positive CV would indicate that the project is under budget.
A CV of zero would indicate that the project is exactly on budget.
Note: The Planned Value ($PV$) of $\$28,000$ is used for calculating Schedule Variance ($SV = EV - PV$), but it is not used in the calculation for Cost Variance.