New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 118 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 118 Topic 12 Discussion

CAPM Exam Topic 12 Question 118 Discussion:
Question #: 118
Topic #: 12

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?


A.

Project charter, business documents, and project management plan


B.

Agreements, scope baseline, and project management plan


C.

Project charter, business case, and project management plan


D.

Work performance data, enterprise environmental factors, and project management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.