Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 118 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 118 Topic 12 Discussion

CAPM Exam Topic 12 Question 118 Discussion:
Question #: 118
Topic #: 12

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?


A.

List of identified risks, potential risk owners, list of potential risk response


B.

List of identified risks, list of causes, list of risk categories


C.

Short risk titles, list of potential risk owners, list of impacts on objectives


D.

List of activities affected, list of potential risk responses, list of causes


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.