Question #: 316
Topic #: 32

What is the main purpose of Project Quality Management?


A.

To meet customer requirements by overworking the team


B.

To fulfill project schedule objectives by rushing planned inspections


C.

To fulfill project requirements of both quality and grade


D.

To exceed customer expectations