PMI Certified Associate in Project Management (CAPM) CAPM Question # 316 Topic 32 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 316 Topic 32 Discussion

CAPM Exam Topic 32 Question 316 Discussion:
Question #: 316
Topic #: 32

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?


A.

Project Communications Management


B.

Project Integration Management


C.

Project Risk Management


D.

Project Scope Management