Question #: 316
Topic #: 32

A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two)


A.

Project audit


B.

Deliverable acceptance


C.

Risk register tracking


D.

Stakeholder mapping


E.

Issue log update