PMI Certified Associate in Project Management (CAPM) CAPM Question # 316 Topic 32 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 316 Topic 32 Discussion

CAPM Exam Topic 32 Question 316 Discussion:
Question #: 316
Topic #: 32

Risk responses reflect an organization's perceived balance between:


A.

risk taking and risk avoidance.


B.

known risk and unknown risk.


C.

identified risk and analyzed risk.


D.

varying degrees of risk.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer: