CAPM Exam Topic 34 Question 333 Discussion:
Question #: 333
Topic #: 34

Which of these statements is true of subsidiary management plans?


A.

Subsidiary management plans are mandatory for any project


B.

Subsidiary management plans use the project charier as input


C.

Subsidiary management plans can be independently managed


D.

Subsidiary management plans do not need regular updates