Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 4 out of 8 pages
Viewing questions 151-200 out of questions
Questions # 151:

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

Options:

A.

Mitigate


B.

Transfer


C.

Share


D.

Avoid


Expert Solution
Questions # 152:

Which of the following is a tool and technique for Estimate Activity Durations?

Options:

A.

Parametric estimating


B.

Monte Carlo analysis


C.

Alternatives analysis


D.

Bottom-up estimating


Expert Solution
Questions # 153:

The individual or group that provides resources and support for a project and is accountable for success is the:

Options:

A.

sponsor


B.

customer


C.

business partners


D.

functional managers


Expert Solution
Questions # 154:

An output of Control Schedule is:

Options:

A.

A project schedule network diagram


B.

A schedule management plan


C.

Schedule data


D.

Schedule forecasts


Expert Solution
Questions # 155:

Assigned risk ratings are based upon:

Options:

A.

Root cause analysis.


B.

Risk probability and impact assessment.


C.

Expert judgment.


D.

Revised stakeholders' tolerances.


Expert Solution
Questions # 156:

Change requests are an output from which Project Integration Management process?

Options:

A.

Direct and Manage Project Execution


B.

Develop Project Management Plan


C.

Close Project


D.

Develop Project Charter


Expert Solution
Questions # 157:

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks


B.

Perform Qualitative Risk Analysis


C.

Plan Risk Management


D.

Perform Quantitative Risk Analysis


Expert Solution
Questions # 158:

Which process is included in the Project Integration Management Knowledge Area?

Options:

A.

Manage Project Team


B.

Collect Requirements


C.

Sequence Activities


D.

Direct and Manage Project Work


Expert Solution
Questions # 159:

Which technique is used in Perform Quantitative Risk Analysis?

Options:

A.

Sensitivity analysis


B.

Probability and impact matrix


C.

Risk data quality assessment


D.

Risk categorization


Expert Solution
Questions # 160:

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.


B.

Sequence Activities.


C.

Define Scope.


D.

Control Schedule.


Expert Solution
Questions # 161:

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor


B.

After lessons learned have been documented in contract closure


C.

When the project objectives have been met


D.

After resources have been released


Expert Solution
Questions # 162:

Which illustrates the connection between work that needs to be done and its project team members?

Options:

A.

Work breakdown structure (WBS)


B.

Network diagrams


C.

Staffing management plan


D.

Responsibility assignment matrix (RAM)


Expert Solution
Questions # 163:

The Verify Scope process is primarily concerned with:

Options:

A.

formalizing acceptance of the completed project deliverables.


B.

accuracy of the work deliverables.


C.

formalizing approval of the scope statement.


D.

accuracy of the work breakdown structure (WBS).


Expert Solution
Questions # 164:

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

Options:

A.

Initiating


B.

Monitoring and Controlling


C.

Planning


D.

Closing


Expert Solution
Questions # 165:

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests


B.

work performance information and change requests


C.

project management plan updates and work performance information


D.

issue logs and organizational process assets updates


Expert Solution
Questions # 166:

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

Options:

A.

Methodology


B.

Risk category


C.

Risk attitude


D.

Assumption analysis


Expert Solution
Questions # 167:

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests


B.

Performance reports


C.

Organizational process assets


D.

Project management plan


Expert Solution
Questions # 168:

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

Options:

A.

The customer and functional managers


B.

The risk owners and stakeholders


C.

The sponsors and stakeholders


D.

The project management team


Expert Solution
Questions # 169:

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs


B.

Estimate Activity Resources


C.

Control Costs


D.

Determine Budget


Expert Solution
Questions # 170:

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

Options:

A.

Coaching


B.

Avoidance


C.

Consensus


D.

Influencing


Expert Solution
Questions # 171:

At which point of the project is the uncertainty the highest and the risk of failing the greatest?

Options:

A.

Final phase of the project


B.

Start of the project


C.

End of the project


D.

Midpoint of the project


Expert Solution
Questions # 172:

Which of the following investigates the likelihood that each specific risk will occur?

Options:

A.

Risk register


B.

Risk audits


C.

Risk urgency assessment


D.

Risk probability and impact assessment


Expert Solution
Questions # 173:

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOKĀ® Guide.


B.

there is no single way to manage a project.


C.

project management techniques are risk free.


D.

there is only one way to manage projects successfully.


Expert Solution
Questions # 174:

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

Options:

A.

Collect Requirements


B.

Direct and Manage Project Execution


C.

Monitor and Control Project Work


D.

Develop Project Management Plan


Expert Solution
Questions # 175:

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

Options:

A.

0.45


B.

0.56


C.

0.70


D.

1.36


Expert Solution
Questions # 176:

When is a Salience Model used?

Options:

A.

In a work breakdown structure (WBS)


B.

During quality assurance


C.

In stakeholder analysis


D.

During quality control (QC)


Expert Solution
Questions # 177:

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders


B.

Project sponsor and project stakeholder


C.

Project manager and project team


D.

Project manager and project sponsor


Expert Solution
Questions # 178:

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list


B.

Project plan


C.

Activity duration estimates


D.

Project schedule


Expert Solution
Questions # 179:

An input to the Create WBS process is a:

Options:

A.

project charter.


B.

stakeholder register.


C.

project scope statement.


D.

requirements traceability matrix.


Expert Solution
Questions # 180:

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation


B.

organizational theory


C.

meeting


D.

networking


Expert Solution
Questions # 181:

Which of the following tools or techniques is used for Estimate Activity Durations?

Options:

A.

Critical path method


B.

Rolling wave planning


C.

Precedence diagramming method


D.

Parametric estimating


Expert Solution
Questions # 182:

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Options:

A.

Customer request


B.

Market demand


C.

Technological advance


D.

Strategic opportunity


Expert Solution
Questions # 183:

The stakeholder register is an output of:

Options:

A.

Identify Stakeholders.


B.

Plan Stakeholder Management.


C.

Control Stakeholder Engagement.


D.

Manage Stakeholder Engagement.


Expert Solution
Questions # 184:

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

Options:

A.

budget at completion (BAC)


B.

earned value management (EVM)


C.

to-complete performance index


D.

cost performance index


Expert Solution
Questions # 185:

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

Options:

A.

Organizational standard processes


B.

Marketplace conditions


C.

Historical information


D.

Templates


Expert Solution
Questions # 186:

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.


B.

Control Procurements.


C.

Close Procurements.


D.

Conduct Procurements.


Expert Solution
Questions # 187:

Which of the following techniques is used during Control Scope?

Options:

A.

Cost-benefit analysis


B.

Variance analysis


C.

Reserve analysis


D.

Stakeholder analysis


Expert Solution
Questions # 188:

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Perform Qualitative Risk Analysis


B.

Perform Quantitative Risk Analysis


C.

Plan Risk Management


D.

Plan Risk Responses


Expert Solution
Questions # 189:

Which activity is an input to the Conduct Procurements process?

Options:

A.

Organizational process assets


B.

Resource availability


C.

Perform Integrated Change Control


D.

Team performance assessment


Expert Solution
Questions # 190:

Which schedule network analysis technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning


B.

Fast tracking


C.

Critical chain method


D.

Rolling wave planning


Expert Solution
Questions # 191:

The primary benefit of the Plan Schedule Management process is that it:

Options:

A.

provides guidance to identify time or schedule challenges within the project.


B.

tightly links processes to create a seamless project schedule.


C.

guides how the project schedule will be managed throughout the project.


D.

creates an overview of all activities broken down into manageable subsections.


Expert Solution
Questions # 192:

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03


B.

0.06


C.

0.10


D.

0.50


Expert Solution
Questions # 193:

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

Options:

A.

improvement


B.

program


C.

result


D.

portfolio


Expert Solution
Questions # 194:

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

Options:

A.

appetite


B.

tolerance


C.

threshold


D.

management


Expert Solution
Questions # 195:

Project management processes ensure the:

Options:

A.

alignment with organizational strategy


B.

efficient means to achieve the project objectives


C.

performance of the project team


D.

effective flow of the project throughout its life cycle


Expert Solution
Questions # 196:

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Options:

A.

Strong


B.

Weak


C.

Managed


D.

Balanced


Expert Solution
Questions # 197:

An output of the Perform Integrated Change Control process is:

Options:

A.

Deliverables.


B.

Validated changes.


C.

The change log.


D.

The requirements traceability matrix.


Expert Solution
Questions # 198:

When closing a project or phase, part of the process may require the use of which type of analysis?

Options:

A.

Reserve analysis


B.

Regression analysis


C.

Document analysis


D.

Product analysis


Expert Solution
Questions # 199:

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:

Options:

A.

Level of control.


B.

Communication channels.


C.

Scope.


D.

Strategic alignment.


Expert Solution
Questions # 200:

Specification of both the deliverables and the processes is the focus of:

Options:

A.

Change control


B.

Configuration control


C.

Project monitoring and control


D.

Issue control


Expert Solution
Viewing page 4 out of 8 pages
Viewing questions 151-200 out of questions