Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 4 out of 8 pages
Viewing questions 151-200 out of questions
Questions # 151:

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

Options:

A.

Project Cost Management


B.

Project Integration Management


C.

Project Resources Management


D.

Project Scope Management


Expert Solution
Questions # 152:

What are the objectives of Initiation processes?

Options:

A.

Initiation processes are performed in order to develop the project charier and Identify stakeholders.


B.

Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.


C.

Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders ' goals.


D.

Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.


Expert Solution
Questions # 153:

A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?

Options:

A.

Resource management plan and lessons learned register


B.

Resource management plan and cost baseline


C.

Resource management plan and procurement management plan


D.

Resource management plan and preassignment


Expert Solution
Questions # 154:

Plan Schedule Management is a process in which Knowledge Area?

Options:

A.

Project Scope Management


B.

Project Human Resource Management


C.

Project Integration Management


D.

Project Time Management


Expert Solution
Questions # 155:

Those who enter into a contractual agreement to provide services necessary for a project are:

Options:

A.

buyers


B.

sellers


C.

business partners


D.

product users


Expert Solution
Questions # 156:

Which of the following is a tool or technique used in the Determine Budget process?

Options:

A.

Variance analysis


B.

Three-point estimating


C.

Bottom-up estimating


D.

Historical relationships


Expert Solution
Questions # 157:

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.


B.

Contain the standard activity list.


C.

Document and support the project change requests.


D.

Prescribe the level of detail needed to manage the work.


Expert Solution
Questions # 158:

What is a tailoring consideration in Project Integration Management?

Options:

A.

Validation and control


B.

Benefits


C.

Technology support


D.

Physical location


Expert Solution
Questions # 159:

A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?

Options:

A.

Collective decision making


B.

Multicriteria decision analysis


C.

Mind mapping


D.

Affinity diagram


Expert Solution
Questions # 160:

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

Options:

A.

Push


B.

Pull


C.

Interactive


D.

Iterative


Expert Solution
Questions # 161:

An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two)

Options:

A.

Daily scrum


B.

Increments


C.

Sprint retrospective


D.

Sprint backlog


E.

Product backlog


Expert Solution
Questions # 162:

Which is one of the determining factors used to calculate CPI?

Options:

A.

EV


B.

SPI


C.

PV


D.

ETC


Expert Solution
Questions # 163:

What is project management?

Options:

A.

A logical grouping of project management inputs, outputs, tools, and techniques


B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements


C.

Launching a process that can result in the authorization of a new project


D.

A formal, approved document that defines how the project is executed, monitored, and controlled


Expert Solution
Questions # 164:

During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?

Options:

A.

Move these user stories back to the product backlog for reprioritization.


B.

Remove these user stories as they are not important.


C.

Advance these user stories to the top of the next sprint backlog.


D.

Complete these user stories in the current sprint and extend the sprint length.


Expert Solution
Questions # 165:

In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process ' ?

Options:

A.

Assumption log


B.

Milestone list


C.

Business case


D.

Risk register


Expert Solution
Questions # 166:

A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

Options:

A.

Identify the crashed project schedule to find the shortest duration to complete the project.


B.

Identify the longest activity path in the schedule with the shortest possible duration.


C.

Identify the tasks with float duration, which do not impact the duration of the project.


D.

Identify the path through the schedule with leveled resources and the shortest duration.


Expert Solution
Questions # 167:

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

Options:

A.

Feedback analysis


B.

Stakeholder analysis


C.

Communication management plan


D.

Stakeholder management plan


Expert Solution
Questions # 168:

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Options:

A.

Checksheets


B.

Histograms


C.

Flowcharts


D.

Control charts


Expert Solution
Questions # 169:

Match each Project Cost Management process with its appropriate keyword

Question # 169


Expert Solution
Questions # 170:

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.


B.

project management plan updates.


C.

change requests.


D.

work performance information.


Expert Solution
Questions # 171:

Which tool or technique is used in validating the scope of a project?

Options:

A.

Facilitated workshops


B.

Interviews


C.

Inspection


D.

Meetings


Expert Solution
Questions # 172:

Which of the following are components of the technical project management skill?

Options:

A.

Ability to explain business aspects of the project, business strategy, goals and objectives, and business value.


B.

Ability to deal with people, to be collaborative, and to apply persuasion and negotiation.


C.

Ability to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy.


D.

Ability to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors.


Expert Solution
Questions # 173:

An input to the Manage Project Team process is:

Options:

A.

Work performance reports.


B.

Change requests.


C.

Activity resource requirements.


D.

Enterprise environmental factors.


Expert Solution
Questions # 174:

What organizational asset can influence the Plan Risk Management process?

Options:

A.

Corporate policies and procedures for social media, ethics, and security


B.

Organizational risk policy


C.

Stakeholder register templates and instructions


D.

Organizational communication requirements


Expert Solution
Questions # 175:

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

Options:

A.

Histograms


B.

Scatter diagrams


C.

Flowcharts


D.

Checksheets


Expert Solution
Questions # 176:

The initial development of a Project Scope Management plan uses which technique?

Options:

A.

Alternatives identification


B.

Scope decomposition


C.

Expert judgment


D.

Product analysis


Expert Solution
Questions # 177:

The staffing management plan is part of the:

Options:

A.

organizational process assets.


B.

resource calendar.


C.

human resource plan.


D.

Develop Project Team process.


Expert Solution
Questions # 178:

Projects are undertaken by an organization to support the:

Options:

A.

Product performance.


B.

Budget process.


C.

Collective capabilities.


D.

Organizational strategy.


Expert Solution
Questions # 179:

A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?

Options:

A.

Earned Schedule + Actual Time


B.

Actual Time - Earned Schedule


C.

Planned Value - Earned Value


D.

Earned Value - Planned Value


Expert Solution
Questions # 180:

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

Options:

A.

Monitor project stakeholder relationships using engaging strategies and plans


B.

Send all project documents to stakeholders each time they are modified


C.

Schedule monthly meetings with the stakeholders, including team members


D.

Engage only with the project sponsors


Expert Solution
Questions # 181:

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

Options:

A.

2.0


B.

45


C.

0.5


D.

15


Expert Solution
Questions # 182:

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?

Options:

A.

Project plan


B.

Business case


C.

Budget requirement


D.

Project charter


Expert Solution
Questions # 183:

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Options:

A.

Strong


B.

Weak


C.

Managed


D.

Balanced


Expert Solution
Questions # 184:

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

Options:

A.

2


B.

3


C.

4


D.

6


Expert Solution
Questions # 185:

The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?

Options:

A.

Plan Cost Management


B.

Estimate Activity Resources


C.

Estimate Costs


D.

Determine Budget


Expert Solution
Questions # 186:

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

Options:

A.

Add the milestones to the risk register, as time is short.


B.

Add the two milestones to the project plan, as they are mandatory.


C.

Calculate the duration of the two milestones stated in the contract.


D.

Start the project as soon as possible, as time is short.


Expert Solution
Questions # 187:

The project manager has following information about duration for an activity:

* Most likely [tM] - 15 days

* Pessimistic [tP] - 20 days

* Optimistic [tO] - 10 days

What is the estimated duration of this activity, according to the triangular distribution technique?

Options:

A.

10 days


B.

15 days


C.

12.5 days


D.

5 days


Expert Solution
Questions # 188:

One of the tools and techniques of the Manage Project Team process is:

Options:

A.

organization charts.


B.

ground rules.


C.

organizational theory,


D.

conflict management.


Expert Solution
Questions # 189:

An input of the Control Schedule process is the:

Options:

A.

resource calendar.


B.

activity list.


C.

risk management plan.


D.

organizational process assets.


Expert Solution
Questions # 190:

When the business objectives of an organization change, project goals need to be:

Options:

A.

realigned.


B.

performed.


C.

improved.


D.

controlled.


Expert Solution
Questions # 191:

What is the best tool to calculate the critical path on a project?

Options:

A.

Critical chain method


B.

Graphical evaluation and review technique (GERT) diagram


C.

Gantt chart


D.

Project network diagram


Expert Solution
Questions # 192:

Conflict should be best addressed in which manner?

Options:

A.

Early, in private, using a direct, collaborative approach


B.

Early, in public, using an indirect, collaborative approach


C.

Early, in private, using an indirect, cooperative approach


D.

As late as possible, in public, using a direct, confrontational approach


Expert Solution
Questions # 193:

Assigned risk ratings are based upon:

Options:

A.

Root cause analysis.


B.

Risk probability and impact assessment.


C.

Expert judgment.


D.

Revised stakeholders ' tolerances.


Expert Solution
Questions # 194:

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

Options:

A.

Verified deliverables.


B.

Validated deliverables.


C.

Acceptance criteria.


D.

Activity resource requirements.


Expert Solution
Questions # 195:

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan


B.

Risk register


C.

Change requests


D.

Risk response plan


Expert Solution
Questions # 196:

An output of the Develop Project Team process is:

Options:

A.

change requests


B.

team performance assessments


C.

project staff assignments


D.

project documents updates


Expert Solution
Questions # 197:

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

Options:

A.

Develop Schedule


B.

Control Schedule


C.

Estimate Activity Durations


D.

Define Activities


Expert Solution
Questions # 198:

What is main purpose of Project Quantity Management?

Options:

A.

To meet customer requirements by overworking the team


B.

To fulfill project schedule objectives by rushing planned inspections


C.

To fulfill project requirements of both quality and grade


D.

To exceed customer expectations


Expert Solution
Questions # 199:

After defining activities in project schedule management, which processes should a project manager follow?

Options:

A.

Sequence Activities and Estimate Activity Durations


B.

Estimate Activity Durations and Control Schedule


C.

Develop Schedule and Control schedule


D.

Review Activities and Develop Schedule


Expert Solution
Questions # 200:

In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

Options:

A.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.


B.

Make sure proper testing gets completed to minimize the risk highlighted.


C.

Add this risk to the lessons learned register on project completion.


D.

Add the stakeholder to the stakeholder register and add the risk to the risk register.


Expert Solution
Viewing page 4 out of 8 pages
Viewing questions 151-200 out of questions