Which of the following are three inputs to the risk register?
Which of the following is a project constraint?
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
Activity cost estimates are quantitative assessments of the probable costs required to:
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
What happens to a stakeholder's project influence over time?
The total of the planned value (PV) is also known as:
Which of the following can be used as an input for Define Scope?
Which activity may occur at project or phase closure?
In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.
What should the project manager do?
A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.
Which method should be used in this situation?
What is purpose of using the building information model (BIM) in software tools in the construction field?
What tool or technique will establish expected behaviors for project team members?
A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity's prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.
How should the project manager proceed?
An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage.
What effective tools should the project teams use to collaborate?
A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?
What specific quality considerations should be examined while completing Quality Management plan?
A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.
Which of the following project delivery approaches should be recommended?
How does planning for prevention costs assist in meeting stakeholder needs and expectations, while still providing required performance and reliability?
On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.
What is the advantage of using this tool?
After winning a large government contract, a company needs to hire a portfolio manager What vital qualification should candidates possess?
In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process'?
Which of the following are components of the project management plan?
In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost
An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.
Which of the following changes has caused this loss in productivity?
A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?
Which document can help a project manager to leverage historical project information?
An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?
How can working in iterations increase the quality of the product being built?
Which is an aspect of the requirements management plan?
What purpose does the hierarchical focus of stakeholder communications serve?
Who should the stakeholders consult to discuss concerns about the current work package?
A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?
Which statement describes the various purposes of project scheduling?
One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?
A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?
Which of these is true project integration management?
A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
What process is performed periodically throughout the project as needed?
The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?
An organization that is being interviewed online has recently experienced a severe network outage. Consequently, the organization has stated that it is required to have a working data network.
Which classification should be assigned to data network requirements?
What is the goal of the control quality process in project management?
A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.
Which method should the project manager adopt?
A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?
Project managers plan a key role performing integration on the project what are the three different levels of integration?
Most experienced project managers know that:
The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:
What is the function of a Project Management Office (PMO)?