Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI CAPM CAPM Questions and answers with CertsForce

Viewing page 4 out of 8 pages
Viewing questions 151-200 out of questions
Questions # 151:

When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what should the practitioner do first?

Options:

A.

Develop the feature as a parallel work package.


B.

Shorten the current work period and begin the new work.


C.

Ask a dedicated team member to complete it immediately.


D.

Prioritize it in the requirements list for the next work period.


Expert Solution
Questions # 152:

An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?

Options:

A.

Product and sprint backlog


B.

Key performance indicators (KPIs) and baseline


C.

Increments and bottlenecks


D.

Burndown and burnup charts


Expert Solution
Questions # 153:

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

Options:

A.

-700


B.

-200


C.

200


D.

500


Expert Solution
Questions # 154:

A project manager should communicate to stakeholders about resolved project issues by updating the:

Options:

A.

project records


B.

project reports


C.

stakeholder notifications


D.

stakeholder register


Expert Solution
Questions # 155:

Creating the project scope statement is part of which process?

Options:

A.

Manage Scope


B.

Collect Requirements


C.

Define Scope


D.

Validate Scope


Expert Solution
Questions # 156:

Under which circumstances should multiple projects be grouped in a program?

Options:

A.

When they are needed to accomplish a set of goals and objectives for an organization


B.

When they have the same project manager and the same organizational unit


C.

When they have the same scope, budget, and schedule


D.

When they are from the same unit of the organization


Expert Solution
Questions # 157:

An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.

Which two of the following items should be included in the planning? (Choose two)

Options:

A.

Daily scrum


B.

Sprint backlog


C.

Sprint review


D.

Increments


E.

Sprint retrospective


Expert Solution
Questions # 158:

Which two of the following can be used as communication tools between the business analyst and the rest of the project team? (Choose two)

Options:

A.

Project management plan


B.

Pareto chart


C.

Gantt chart


D.

Responsible, accountable, consult, inform (RACI) matrix


E.

Process flows


Expert Solution
Questions # 159:

Which are the most important competencies required for a project manager?

Options:

A.

Leadership, bilingualism, experience, and technical Knowledge


B.

PMP certification, experience, technical Knowledge, and post-graduate education


C.

Leadership, strategic and business management, project management knowledge, and technical knowledge


D.

Communication skills, project management knowledge, PMP certification, and availability to travel


Expert Solution
Questions # 160:

What can a project manager review to understand the status of a project?

Options:

A.

Work breakdown structure (WBS) status


B.

Quality and technical performance measures


C.

Cost and scope baselines


D.

Business case completeness


Expert Solution
Questions # 161:

How many Project Management Process Groups are there?

Options:

A.

3


B.

4


C.

5


D.

6


Expert Solution
Questions # 162:

What prototyping technique shows a sequence or navigations through a series of images or illustrations?

Options:

A.

Storyboarding


B.

Wireframes


C.

Data simulation


D.

Report prototyping


Expert Solution
Questions # 163:

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

Options:

A.

Sensitivity analysis


B.

Three-point estimate


C.

Modeling and simulation


D.

Expected monetary value analysis


Expert Solution
Questions # 164:

Tools and techniques used for Plan Communications include the communication:

Options:

A.

requirements analysis, communication technology, communication models, and communication methods.


B.

methods, stakeholder register, communication technology, and communication models.


C.

requirements, communication technology, communication requirements analysis, and communication methods.


D.

management plan, communication technology, communication models, and communication requirements analysis.


Expert Solution
Questions # 165:

What tool should a project manager use to efficiently manage project resources?

Options:

A.

List of project resources


B.

Resource breakdown structure


C.

Resources detailed in the project scope


D.

Resource requirements


Expert Solution
Questions # 166:

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

Options:

A.

Scope plan


B.

Product scope


C.

Scope management plan


D.

Scope baseline


Expert Solution
Questions # 167:

Which risk response strategy is common for both positive and negative risks?

Options:

A.

Share


B.

Accept


C.

Mitigate


D.

Transfer


Expert Solution
Questions # 168:

The project management processes presented in the PMBOK Guide® should:

Options:

A.

always be applied uniformly.


B.

be selected as appropriate by the sponsor.


C.

be selected as appropriate by the project team.


D.

be applied based on ISO guidelines.


Expert Solution
Questions # 169:

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03


B.

0.06


C.

0.10


D.

0.50


Expert Solution
Questions # 170:

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Options:

A.

100


B.

120


C.

1,000


D.

1,200


Expert Solution
Questions # 171:

Which Process Group and Knowledge Area include the Sequence Activities process?

Options:

A.

Executing Process Group and Project Time Management


B.

Executing Process Group and Project Cost Management


C.

Planning Process Group and Project Time Management


D.

Planning Process Group and Project Cost Management


Expert Solution
Questions # 172:

What is the definition of Direct and Manage Project Execution?

Options:

A.

Integrating all planned activities


B.

Performing the activities included in the plan


C.

Developing and maintaining the plan


D.

Execution of deliverables


Expert Solution
Questions # 173:

An output of the Develop Project Team process is:

Options:

A.

change requests


B.

team performance assessments


C.

project staff assignments


D.

project documents updates


Expert Solution
Questions # 174:

Which is an input to the Verify Scope process?

Options:

A.

Performance report


B.

Work breakdown structure (WBS)


C.

Requested changes


D.

Project management plan


Expert Solution
Questions # 175:

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

Options:

A.

Verified deliverables.


B.

Validated deliverables.


C.

Acceptance criteria.


D.

Activity resource requirements.


Expert Solution
Questions # 176:

Typical outcomes of a project include:

Options:

A.

Products, services, and improvements.


B.

Products, programs, and services.


C.

Improvements, portfolios, and services.


D.

Improvements, processes, and products.


Expert Solution
Questions # 177:

Which contract type is least desirable to a vendor?

Options:

A.

Fixed price with economic price adjustment (FPEPA)


B.

Firm fixed price (FFP)


C.

Cost plus fixed fee (CPFF >


D.

Cost plus award fee (CPAF >


Expert Solution
Questions # 178:

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

Options:

A.

Eleven weeks


B.

Nine weeks


C.

Eight weeks


D.

Ten weeks


Expert Solution
Questions # 179:

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.


B.

Sequence Activities.


C.

Define Scope.


D.

Control Schedule.


Expert Solution
Questions # 180:

When planning communications management what input identifies key stakeholders?

Options:

A.

Work performance information


B.

Project schedule


C.

Project charter


D.

Work performance reports


Expert Solution
Questions # 181:

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Options:

A.

Facilitation techniques


B.

Expert judgment


C.

Analytical techniques


D.

Variance analysis


Expert Solution
Questions # 182:

In a project using agile methodology, who may perform the quality control activities?

Options:

A.

A group of quality experts at specific times during the project


B.

The project manager only


C.

All team members throughout the project life cycle


D.

Selected stakeholders at specific times during the project


Expert Solution
Questions # 183:

An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage.

What effective tools should the project teams use to collaborate?

Options:

A.

Adopt an iterative development approach and conduct virtual meetings.


B.

Arrange frequent colocated meetings and let the teams work together.


C.

Focus on developing products by only using teams that are colocated.


D.

Benchmark and adopt best practices that are being used by the competition.


Expert Solution
Questions # 184:

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

Options:

A.

Work breakdown structure (WBS)


B.

Approval from the stakeholders


C.

Feasibility study of the solution


D.

Root cause analysis of the problem


Expert Solution
Questions # 185:

Which of the following lists represents trends and emerging practices in Project Risk Management?

Options:

A.

Integrated risk management, non-event risks, and project resilience


B.

Representation of uncertainty, strategies for opportunities, and strategies for overall project risk


C.

Dormancy, proximity, and propinquity


D.

Simulation, sensitivity analysis, and decision tree analysis


Expert Solution
Questions # 186:

Which of the following can a project manager conduct if they have a stakeholder who is unresponsive and/or unsupportive?

Options:

A.

Interactive communications


B.

Pull communications


C.

Push communications


D.

Communication style assessment


Expert Solution
Questions # 187:

Which of the following set of elements is part of an effective communications management plan?

Options:

A.

Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information


B.

Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology


C.

Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology


D.

Glossary of common terminology, constraints denved from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan


Expert Solution
Questions # 188:

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)


B.

Fixed Price Incentive Fee (FPIF)


C.

Cost Pius Award Re (CPAF)


D.

Time and Material (TandM)


Expert Solution
Questions # 189:

Which cost is associated with nonconformance?

Options:

A.

Liabilities


B.

Inspections


C.

Training


D.

Equipment


Expert Solution
Questions # 190:

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

Options:

A.

Cost-reimbursable


B.

Time and material


C.

Fixed price or lump-sum


D.

Cost-plus-fixed-fee


Expert Solution
Questions # 191:

Which of the following events would result in a baseline update?

Options:

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.


B.

A customer has approved a change request broadening the project scope and increasing the budget.


C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.


D.

One of the key project team resources has left the team and no replacement is available.


Expert Solution
Questions # 192:

Which is the order of steps in the Procurement Management process?

Options:

A.

Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements


B.

Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements


C.

Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors


D.

Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements


Expert Solution
Questions # 193:

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Options:

A.

Estimate Costs


B.

Control Costs


C.

Determine Budget


D.

Plan Cost Management


Expert Solution
Questions # 194:

Which is the correct hierarchy in a project environment, from most to least Inclusive?

Options:

A.

Projects, portfolios, then programs


B.

Portfolios, programs, then projects


C.

Portfolios, projects, then programs


D.

Projects, programs, then portfolios


Expert Solution
Questions # 195:

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition


B.

Modeling techniques


C.

Resource optimization


D.

Meetings


Expert Solution
Questions # 196:

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

Options:

A.

Forming


B.

Storming


C.

Norming


D.

Performing


Expert Solution
Questions # 197:

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

Options:

A.

organizational skills


B.

technical skills


C.

communication skills


D.

hard skills


Expert Solution
Questions # 198:

Which role does the project manager resemble best?

Options:

A.

Orchestra conductor


B.

Facilities supervisor


C.

Functional manager


D.

School principal


Expert Solution
Questions # 199:

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

Options:

A.

divided among each of the phases or subprojects.


B.

repeated for each of the phases or subprojects.


C.

linked to specific phases or subprojects.


D.

integrated for specific phases or subprojects.


Expert Solution
Questions # 200:

A risk that arises as a direct result of implementing a risk response is called a:

Options:

A.

contingent risk


B.

residual risk


C.

potential risk


D.

secondary risk


Expert Solution
Viewing page 4 out of 8 pages
Viewing questions 151-200 out of questions