A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?
A.
Add the milestones to the risk register, as time is short.
B.
Add the two milestones to the project plan, as they are mandatory.
C.
Calculate the duration of the two milestones stated in the contract.
D.
Start the project as soon as possible, as time is short.