Question #: 190
Topic #: 20

An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?


A.

Product and sprint backlog


B.

Key performance indicators (KPIs) and baseline


C.

Increments and bottlenecks


D.

Burndown and burnup charts