According to the PMBOK® Guide and The Standard for Portfolio Management, projects exist to deliver value and achieve the strategic goals of an organization.
Strategic Alignment: A fundamental principle of project management is that projects are the primary vehicle for executing an organization ' s strategy. When the executive leadership shifts the business objectives (due to market changes, financial shifts, or new regulations), the ongoing and planned projects must be evaluated.
The Realignment Process: This involves reviewing the Project Charter and the Business Case to ensure they still support the updated organizational strategy. If a project no longer contributes to the new objectives, it may be changed, rescoped, or even terminated.
Portfolio Management Role: High-level alignment is typically managed at the portfolio level, where the " mix " of projects is adjusted to ensure the highest return on investment relative to the current strategic direction.
Comparison with other options:
B. Performed: Simply continuing to " perform " or execute a project that is no longer aligned with business goals is a waste of organizational resources (sunk cost fallacy).
C. Improved: While quality improvement is always a goal, " improving " a project ' s performance does not solve the fundamental issue of the project no longer serving the organization ' s revised strategic purpose.
D. Controlled: " Controlled " refers to the Monitoring and Controlling Process Group, which ensures the project stays on its current baseline. However, if the business objectives change, the baseline itself must be questioned and realigned before it can be controlled.