PMI Certified Associate in Project Management (CAPM) CAPM Question # 191 Topic 20 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 191 Topic 20 Discussion

CAPM Exam Topic 20 Question 191 Discussion:
Question #: 191
Topic #: 20

The primary benefit of the Plan Schedule Management process is that it:


A.

provides guidance to identify time or schedule challenges within the project.


B.

tightly links processes to create a seamless project schedule.


C.

guides how the project schedule will be managed throughout the project.


D.

creates an overview of all activities broken down into manageable subsections.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.