Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 191 Topic 20 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 191 Topic 20 Discussion

CAPM Exam Topic 20 Question 191 Discussion:
Question #: 191
Topic #: 20

Which of the following events would result in a baseline update?


A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.


B.

A customer has approved a change request broadening the project scope and increasing the budget.


C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.


D.

One of the key project team resources has left the team and no replacement is available.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.