Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 191 Topic 20 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 191 Topic 20 Discussion

CAPM Exam Topic 20 Question 191 Discussion:
Question #: 191
Topic #: 20

A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?


A.

Identify the crashed project schedule to find the shortest duration to complete the project.


B.

Identify the longest activity path in the schedule with the shortest possible duration.


C.

Identify the tasks with float duration, which do not impact the duration of the project.


D.

Identify the path through the schedule with leveled resources and the shortest duration.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.