According to the PMBOK® Guide, a Baseline (Scope, Schedule, or Cost) is the approved version of a project plan. It can only be changed through formal Change Control procedures and is used as a basis for comparison to actual results.
Approved Change Requests: When a change request is formally approved through the Perform Integrated Change Control process, and that change affects the project ' s scope, schedule, or cost, the corresponding baselines must be updated. This ensures that the " yardstick " used to measure performance reflects the new, agreed-upon reality of the project.
The Baseline ' s Purpose: The baseline exists to track variances. If you changed the baseline every time a project was late or a risk occurred (Options A, C, and D), you would lose the ability to measure how far the project has drifted from the original plan.
Analysis of Other Options:
A. A project is behind schedule...: This is often referred to as " re-baselining to hide delays. " Baselines should not be updated simply because performance is poor; the baseline must remain to show the extent of the delay.
C. A risk occurs, resulting in a delay: When a risk occurs, it is handled using contingency reserves or workarounds. While it impacts the actual data, it does not automatically change the baseline unless a formal change request is approved to modify the project ' s end date.
D. Resource leaves with no replacement: This is a project constraint or issue. While it will likely cause a variance in the schedule and cost, the baseline remains the same so the project manager can report the negative impact of that resource loss against the original plan.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit