New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 191 Topic 20 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 191 Topic 20 Discussion

CAPM Exam Topic 20 Question 191 Discussion:
Question #: 191
Topic #: 20

What process is performed periodically throughout the project as needed?


A.

Plan Risk Management


B.

Plan Communications Management


C.

Plan Resource Management


D.

Plan Cost Management


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.