Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 188 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 188 Topic 19 Discussion

CAPM Exam Topic 19 Question 188 Discussion:
Question #: 188
Topic #: 19

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:


A.

risk management plan


B.

human resource management plan


C.

scope management plan


D.

procurement management plan


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.