CAPM Exam Topic 19 Question 188 Discussion:
Question #: 188
Topic #: 19

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?


A.

Schedule network analysis


B.

Reserve analysis


C.

Alternative analysis


D.

Variance analysis