New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 187 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 187 Topic 19 Discussion

CAPM Exam Topic 19 Question 187 Discussion:
Question #: 187
Topic #: 19

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?


A.

Project plan


B.

Business case


C.

Budget requirement


D.

Project charter


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.