PMI Certified Associate in Project Management (CAPM) CAPM Question # 187 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 187 Topic 19 Discussion

CAPM Exam Topic 19 Question 187 Discussion:
Question #: 187
Topic #: 19

Which of the following techniques is used during Control Scope?


A.

Cost-benefit analysis


B.

Variance analysis


C.

Reserve analysis


D.

Stakeholder analysis


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.