Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 187 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 187 Topic 19 Discussion

CAPM Exam Topic 19 Question 187 Discussion:
Question #: 187
Topic #: 19

The project manager has following information about duration for an activity:

* Most likely [tM] - 15 days

* Pessimistic [tP] - 20 days

* Optimistic [tO] - 10 days

What is the estimated duration of this activity, according to the triangular distribution technique?


A.

10 days


B.

15 days


C.

12.5 days


D.

5 days


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.