PMI Certified Associate in Project Management (CAPM) CAPM Question # 176 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 176 Topic 18 Discussion

CAPM Exam Topic 18 Question 176 Discussion:
Question #: 176
Topic #: 18

An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.

Which of the following changes has caused this loss in productivity?


A.

Two of the team members have been working in silos using different methods to validate their performance.


B.

The team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.


C.

The team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.


D.

Two of the team members were asked to do multitasking, which they did not do in the previous two sprints.