Big Cyber Monday Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 177 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 177 Topic 18 Discussion

CAPM Exam Topic 18 Question 177 Discussion:
Question #: 177
Topic #: 18

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?


A.

Predictive


B.

Hybrid


C.

Kanban


D.

Adaptive


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.