PMI Certified Associate in Project Management (CAPM) CAPM Question # 177 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 177 Topic 18 Discussion

CAPM Exam Topic 18 Question 177 Discussion:
Question #: 177
Topic #: 18

Who selects the appropriate processes for a project?


A.

Project stakeholders


B.

Project sponsor and project stakeholder


C.

Project manager and project team


D.

Project manager and project sponsor


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.