PMI Certified Associate in Project Management (CAPM) CAPM Question # 312 Topic 32 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 312 Topic 32 Discussion

CAPM Exam Topic 32 Question 312 Discussion:
Question #: 312
Topic #: 32

A project manager is reviewing a past project with similar.... team choosing for tailoring?

A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?


A.

Policy compliance and auditing


B.

Standards and compliance


C.

Review of lessons learned


D.

Test and inspection planning


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.