Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 313 Topic 32 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 313 Topic 32 Discussion

CAPM Exam Topic 32 Question 313 Discussion:
Question #: 313
Topic #: 32

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?


A.

Add the milestones to the risk register, as time is short.


B.

Add the two milestones to the project plan, as they are mandatory.


C.

Calculate the duration of the two milestones stated in the contract.


D.

Start the project as soon as possible, as time is short.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.