PMI Certified Associate in Project Management (CAPM) CAPM Question # 314 Topic 32 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 314 Topic 32 Discussion

CAPM Exam Topic 32 Question 314 Discussion:
Question #: 314
Topic #: 32

Which of the following is a project constraint?


A.

Twenty-five percent staff turnover is expected.


B.

The technology to be used is cutting-edge.


C.

Project leadership may change due to volatile political environment.


D.

The product is needed in 250 days.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.