New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 379 Topic 38 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 379 Topic 38 Discussion

CAPM Exam Topic 38 Question 379 Discussion:
Question #: 379
Topic #: 38

At which point of the project is the uncertainty the highest and the risk of failing the greatest?


A.

Final phase of the project


B.

Start of the project


C.

End of the project


D.

Midpoint of the project


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.