Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 175 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 175 Topic 18 Discussion

CAPM Exam Topic 18 Question 175 Discussion:
Question #: 175
Topic #: 18

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?


A.

Slack


B.

Float


C.

Lag


D.

Lead


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.