Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 175 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 175 Topic 18 Discussion

CAPM Exam Topic 18 Question 175 Discussion:
Question #: 175
Topic #: 18

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost


A.

High-level deliverables


B.

Success criteria


C.

Project objectives


D.

Phase transitions


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.