Big Cyber Monday Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 178 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 178 Topic 18 Discussion

CAPM Exam Topic 18 Question 178 Discussion:
Question #: 178
Topic #: 18

Which document can help a project manager to leverage historical project information?


A.

Lessons learned register


B.

Schedule baseline


C.

Work performance data


D.

Deliverable acceptance forms


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.