Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 178 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 178 Topic 18 Discussion

CAPM Exam Topic 18 Question 178 Discussion:
Question #: 178
Topic #: 18

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?


A.

Eleven weeks


B.

Nine weeks


C.

Eight weeks


D.

Ten weeks


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.