PMI Certified Associate in Project Management (CAPM) CAPM Question # 178 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 178 Topic 18 Discussion

CAPM Exam Topic 18 Question 178 Discussion:
Question #: 178
Topic #: 18

Which of the following is an output of the Define Activities process?


A.

Activity list


B.

Project plan


C.

Activity duration estimates


D.

Project schedule


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.