Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 179 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 179 Topic 18 Discussion

CAPM Exam Topic 18 Question 179 Discussion:
Question #: 179
Topic #: 18

When developing a schedule which tools and techniques should a project manager use?


A.

Schedule Networfc Analysis and Critical Path Method


B.

Activity list and expert Judgement


C.

Milestone Iist and Risk Register


D.

Basis ot estimates and Rolling Wave Planning


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.