PMI Certified Associate in Project Management (CAPM) CAPM Question # 180 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 180 Topic 19 Discussion

CAPM Exam Topic 19 Question 180 Discussion:
Question #: 180
Topic #: 19

The following is a network diagram for a project.

CAPM Question 180

The total float for the project is how many days?


A.

3


B.

5


C.

7


D.

9


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.