Question #: 108
Topic #: 11

A construction project is underway, and during... tasks impacted the painting work

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job What kind ot relationship between the tasks impacted the painting work?


A.

Finish-to-Finish (FF)


B.

Start-to-Finish (SF)


C.

Finish-to-Start(FS)


D.

Start-to-Slart(SS)