A project manager proactively meets with other project managers who manage other projects in the same program. To minimize the impact that other projects within the program may have on their project of what should the project manager be aware?


A.

Demands on the same resources


B.

Requirements that impact the scope


C.

Uncertainty of emerging issues


D.

Project charter