CAPM Exam Topic 14 Question 138 Discussion:
Question #: 138
Topic #: 14

Exhibit A is an example of which of the following types of Sequence Activities?

CAPM Question 138


A.

Activity-on-arrow diagramming


B.

Precedence diagramming


C.

Project schedule network diagramming


D.

Mathematical analysis diagramming