PMI Certified Associate in Project Management (CAPM) CAPM Question # 162 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 162 Topic 17 Discussion

CAPM Exam Topic 17 Question 162 Discussion:
Question #: 162
Topic #: 17

A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.

Which method should be used in this situation?


A.

SAFe®, as it does not allow for scaling work across different teams in the organization.


B.

Extreme Programming (XP), as it does not allow for moving on to new items until the existing items are finished.


C.

Kanban, because the team does not start new work until the existing work is finished.


D.

Scrum, as it allows for completing the whole architecture up front without leaving any technical debt for the future.