CAPM Exam Topic 17 Question 167 Discussion:
Question #: 167
Topic #: 17

A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?


A.

Create a risk in the risk register for each S1 defect and assign actions.


B.

Consult the risk register and implement the risk response actions.


C.

Ask the developers to work longer hours and resolve the defects.


D.

Review the organizational chart to find out who else can sign off UAT.