Big 11.11 Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 51 Topic 6 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 51 Topic 6 Discussion

CAPM Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

The following chart contains information about the tasks in a project.

CAPM Question 51

Based on the chart, what is the schedulevariance (SV) for Task 8?


A.

-2,000


B.

-1,000


C.

1,000


D.

2,000


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.