New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 306 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 306 Topic 31 Discussion

CAPM Exam Topic 31 Question 306 Discussion:
Question #: 306
Topic #: 31

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?


A.

Three weeks


B.

Four weeks


C.

Five weeks


D.

Six weeks


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.