PMI Certified Associate in Project Management (CAPM) CAPM Question # 305 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 305 Topic 31 Discussion

CAPM Exam Topic 31 Question 305 Discussion:
Question #: 305
Topic #: 31

After defining activities in project schedule management, which processes should a project manager follow?


A.

Sequence Activities and Estimate Activity Durations


B.

Estimate Activity Durations and Control Schedule


C.

Develop Schedule and Control schedule


D.

Review Activities and Develop Schedule


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.