PMI Certified Associate in Project Management (CAPM) CAPM Question # 305 Topic 31 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 305 Topic 31 Discussion

CAPM Exam Topic 31 Question 305 Discussion:
Question #: 305
Topic #: 31

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?


A.

$800


B.

$1000


C.

$1250


D.

$1800


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.