Question #: 103
Topic #: 11

What should a product owner do when a new stakeholder is complaining that they are not receiving the relevant financial data regarding the project.


A.

Work with the scrum master to give the stakeholder access to the related information radiator


B.

Invite the stakeholder to the next sprint planning session so they can ask questions of the team


C.

Ask the team to prepare the requested data in the next iteration


D.

Direct the stakeholder to the project team so they can provide more data