Pass the PMI PMI Agile PMI-ACP Questions and answers with CertsForce

Viewing page 1 out of 15 pages
Viewing questions 1-10 out of questions
Questions # 1:
Options:

A.

Coach team members to improve functional specialties and increase overall velocity.


B.

Identify where team processes misalign with accepted Scrum practices.


C.

Facilitate the identification of problems or issues and help the team resolve them.


D.

Review the backlog to ensure that it is prioritized, refined, and properly tasked.


Expert Solution
Questions # 2:

A software development team is working in an environment in which increased competition, demanding customer expectations, and new technological developments pose significant challenges.

How should the team plan improvements to their product?

Options:

A.

Follow the project schedule created at the start of the project.


B.

Hold regular retrospectives and have team members commit to specific actions.


C.

Allow team members to choose improvement items and trust their judgment.


D.

Encourage team members to write code that is tightly coupled together.


Expert Solution
Questions # 3:

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

Options:

A.

Help the team to remove impediments that stall project progress.


B.

Work with the development team to adjust the work plan.


C.

Ask the product owner to assign more resources to the project.


D.

Command and control the team to achieve plan goals.


Expert Solution
Questions # 4:

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.

What should the product owner do?

Options:

A.

Terminate the project to cut losses


B.

Review possible options and make an informed decision to cut losses based on delivered business value


C.

Bring in experts to increase the probability of success


D.

Continue the project, release the product without the failing feature, and fix the feature in a subsequent release


Expert Solution
Questions # 5:

A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.

How should the scrum master help the team to resolve the issue?

Options:

A.

Bring a subject matter expert (SME) from the technology design team to act as a consultant for the team.


B.

Coach the team individually then the whole team during the Sprint review on how to resolve this conflict.


C.

Delegate the decision for the best feature implementation to the most senior team member.


D.

Decide on the technical implementation that best fits the purpose of the technical design.


Expert Solution
Questions # 6:

In a Scrum team, who should be responsible for the budget and release plans?

Options:

A.

The Scrum Master assigns someone on the team to handle the budget, and the Product Owner is responsible for release plans


B.

The finance department is responsible for the budget, and the Product Owner is responsible for release plans


C.

The Scrum team as a whole, as they are self-organizing and share accountability


D.

The Product Owner is responsible for both the budget and the release plans


Expert Solution
Questions # 7:

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

Options:

A.

Focus on performance in the retrospective, then present performance indices and validate with the team.


B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach


C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.


Expert Solution
Questions # 8:

A scrum master is part of a team that has just agreed on the project scope and deliverables for a global, multilingual manufacturing company that has many staff members moving between locations. The team consists of 20 people and the budget is US$5 million. The kickoff meeting is scheduled for the following month.

What should the scrum master do as a first step?

Options:

A.

Organize a sprint planning meeting and include stakeholders.


B.

Invite the product owner to create a stakeholder map.


C.

Identify the key stakeholders at the earliest opportunity.


D.

Invite the key stakeholders to the kickoff meeting.


Expert Solution
Questions # 9:

A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?

Options:

A.

To produce a fast return on investment


B.

To reduce risk as quickly as possible


C.

To gain competitive advantage as soon as possible


D.

To maintain visibility with project stakeholders


Expert Solution
Questions # 10:

As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met.

How should the project management plan be adjusted?

Options:

A.

Holistically at the project level


B.

At the end of each sprint


C.

At a sprint level after each demo


D.

Periodically, at both the release and project level


Expert Solution
Viewing page 1 out of 15 pages
Viewing questions 1-10 out of questions