Questions # 81:

A client has provided their requirements and deadline to the project team. The requirements are confusing, and the team is frustrated.

What should the team ' s servant leader do?

Options:

A.

Try to motivate the team by recounting examples of their past successes.


B.

Ask the team to find user stories from similar projects for this customer.


C.

Ask the team to restate the requirements and review them with the client.


D.

Ask the team to develop user stories and build deliverables based on the requirements.


Expert Solution
Questions # 82:

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.

What should the team do to improve its speed of delivery?

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.

What should the team do to improve its speed of delivery?

Options:

A.

Analyze the process efficiency, cycle time, and lead time of the entire process.


B.

Estimate in story points and pull in new work per the team ' s capacity


C.

Add limits to all columns and only pull work in when the queue is not full.


D.

Create a cumulative flow diagram and start looking for bottlenecks.


Expert Solution
Questions # 83:

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?

Options:

A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.


B.

Ask the team to review the executed tasks and follow up on the upcoming threats.


C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.


D.

Create one sprint to update and follow up on major release risks.


Expert Solution
Questions # 84:

A global subscription-based service is pursuing enterprise agility across digital product development teams. Product teams release updates frequently, but customer usage data and support trends are reviewed only at the end of each quarter. As a result, several low-adoption features continue to receive investment while customer churn gradually increases. Leadership wants the product teams to respond more quickly to changing customer behavior.

What should the agile practitioner recommend?

Options:

A.

Schedule monthly executive reviews to assess customer usage and feedback to support investment decisions.


B.

Integrate customer usage analytics into feature prioritization processes to adjust investment decisions.


C.

Delegate feature prioritization decisions to regional business managers based on customer usage analytics.


D.

Increase the number of features delivered each quarter to drive customer usage and improve overall satisfaction.


Expert Solution
Questions # 85:

A new project has been approved and is critical for an organization. The project sponsor has a limited budget, and the deadline to have all requirements meet the definition of done (DoD) is short.

Which approach should the agile practitioner take to facilitate the project ' s success?

Options:

A.

Set up weekly calls with the key stakeholders to participate in iteration reviews and release decisions.


B.

Analyze the impacts of these constraints on the project followed by a report sent to the sponsor to anticipate any risk of delays.


C.

Set up a meeting with the client to review the scope and timelines to manage expectations.


D.

Encourage the team to build increments and ensure the customer provides early feedback for a minimum viable product.


Expert Solution
Questions # 86:

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team ' s productivity.

How should the team leader exhibit servant leadership?

Options:

A.

By being a change agent


B.

By being the authority on processes


C.

By being a coach


D.

By removing impediments


Expert Solution
Questions # 87:

The initial roadmap and release dates for an agile project were set based on data from similar projects and some expert opinions. Halfway through the project, however, the team’s estimates are different. Based on the team’s velocity, two more iterations were necessary to accomplish the initial scope.

How should the agile lead explain the difference to the project sponsor?

Options:

A.

Explain how many scope changes were requested by the product owner and how many hours the team dedicated to unplanned tasks.


B.

Explain that initial estimates help measure project feasibility but the real estimates depend on how much the team learns in each sprint.


C.

Explain some features and requirements made aspects of the project unique and are not comparable to previous experiences.


D.

Explain the list of materialized risks not considered at the beginning of the project ted to extra work hours and costs.


Expert Solution
Questions # 88:

Question # 88

Answer Options:

Options:

A.

The iteration is in jeopardy.


B.

The team has removed scope.


C.

The iteration is ahead of schedule.


D.

The team ' s velocity is constant.


Expert Solution
Questions # 89:

During the project initiation stage, a team has estimated story points for all user stories. When the project team explained the minimum marketable feature (MMF), however, they were not confident that the solution would actually work.

What can the team do to better manage this situation?

Options:

A.

Deliver the minimum marketable feature (MMF) to customers for feedback.


B.

Write acceptance criteria for each business requirement to conduct proper testing.


C.

Develop test cases based on user stories.


D.

Ask the customer to provide acceptance criteria before developing the user stories.


Expert Solution
Questions # 90:

A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.

What should the servant leader do?

Options:

A.

Coach the company director on agile approaches and good practices.


B.

Ask the product owner to speak to the director because their visits are delaying the project.


C.

Ask the director and team member to leave the room so they can have a private conversation.


D.

Coach the team member on how to report progress to directors and executives.


Expert Solution