Questions # 31:

An agile project leader notices that the team ' s velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.

What can happen as a result?

Options:

A.

The team will be unable to understand the iteration ' s status


B.

The team will be unable to judge the project design ' s validity


C.

The team cannot give accurate updates to management


D.

Team collaboration cannot be measured effectively


Expert Solution
Questions # 32:

The coach on a new agile team notices that one team member is influencing most of the team ' s decisions. What should the coach do?

Options:

A.

Replace the team member with a more collaborative individual.


B.

Permit the team member to continue influencing because agile teams are self-organizing.


C.

Ask probing questions to other team members to encourage dissenting viewpoints.


D.

Intervene if the team ' s velocity drops.


Expert Solution
Questions # 33:

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.


B.

Send the team the latest version of the release plan so they can provide feedback.


C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.


D.

Ensure all iteration goals are fully developed at the beginning of the project.


E.

Refine the product backlog and identify the Minimum Viable Product


Expert Solution
Questions # 34:

What should the Scrum Master do next?

Options:

A.

Monitor the threats and risks while allowing the team member to multitask on both projects


B.

Assign more resources to the sprints to compensate for the absences of the team member


C.

Ensure that the threats and risks are communicated and addressed


D.

Assign fewer stories to the sprints so that the team member can still meet sprint goals


Expert Solution
Questions # 35:

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

Options:

A.

Refocus the sprint review meetings to demonstrate working software and seek feedback on the product.


B.

Reach out to other, more experienced teams to seek input as to how to present the technical details in a more informative manner.


C.

Explain the importance of the technical architecture and design presentations and improve the presentation format.


D.

Invite technical managers and architects who will be a more appropriate audience to their sprint reviews.


Expert Solution
Questions # 36:

What is the risk of using Agile in a distributed team?

Options:

A.

Frequent integration of work produced


B.

Lack of shared knowledge of user stories


C.

Need for more locations to learn Agile


D.

Unclear team structure


Expert Solution
Questions # 37:

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

Options:

A.

The stakeholder who can prevent the project from delivering within budget


B.

The stakeholder who can prevent the project from achieving its goals


C.

The stakeholder who can delay the project


D.

The stakeholder who can work as a friend and help prepare the stakeholder list


Expert Solution
Questions # 38:

A business analyst has been assigned to optimize a process to deliver healthcare services to patients in a clinic. In creating a value stream map, what will the business analyst’s key observations include?

Options:

A.

Process breakdowns and workflow


B.

Wait times and cycle times


C.

Process maps and story points


D.

Activity sequences and earned value (EV)


Expert Solution
Questions # 39:

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

Options:

A.

Help the team to remove impediments that stall project progress.


B.

Work with the development team to adjust the work plan.


C.

Ask the product owner to assign more resources to the project.


D.

Command and control the team to achieve plan goals.


Expert Solution
Questions # 40:

What should a Scrum Master do when one team member falls behind in their tasks?

Options:

A.

Move the task to another team member who has spare capacity in the sprint


B.

Ask the team for suggestions


C.

Privately offer the team member encouragement to meet task commitments


D.

Notify the product owner


Expert Solution