New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 38 Topic 4 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 38 Topic 4 Discussion

PMI-ACP Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.

What should the team do?


A.

Estimate only functional requirements that will impact product quality


B.

Add team resources


C.

Refer the issue to the product owner


D.

Break non-functional requirements into those that can be delivered in the given sprint


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.