PMI-ACP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)


A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.


B.

Send the team the latest version of the release plan so they can provide feedback.


C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.


D.

Ensure all iteration goals are fully developed at the beginning of the project.


E.

Refine the product backlog and identify the Minimum Viable Product


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.