PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 132 Topic 14 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 132 Topic 14 Discussion

PMI-ACP Exam Topic 14 Question 132 Discussion:
Question #: 132
Topic #: 14

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.

How should the agile practitioner explain to senior management the benefits of this approach?


A.

It ensures a consistent level of detail is available in the project schedule


B.

It prevents a wasteful buildup of requirements inventory that may never be processed


C.

It provides a concrete definition of project scope, cost and duration


D.

It allows the team to lock down the stories to be included in a release