Questions # 21:
Options:

A.

Parametric


B.

One-to-one comparison


C.

Affinity


D.

Planning poker


Expert Solution
Questions # 22:

An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)

Options:

A.

Prepare an effort estimation for each story based on their technical expertise.


B.

Compile a list of ideas to improve the velocity of the team so they can plan more story points in the next sprint.


C.

Prepare a list of tasks required to accomplish the goal and the order in which they should be executed.


D.

Read and identify user stories from the backlog that will contribute to accomplishing the goal.


E.

Consider the possible risks of each selected user story and the value they add for the final user.


Expert Solution
Questions # 23:

A product owner wants to create a release plan given the team is working in a chaotic environment. They want to set expectations about what is likely to be developed and in what timeframe for some of the stakeholders.

What should the product owner include in the release plan to achieve this?

Options:

A.

The objective, iterations and underlying features, iteration timelines, other pre-release activities, dependencies, and responsible team.


B.

The key objectives and a brief description of each user story to be delivered in each iteration release timelines and release dependencies


C.

The developer who will work on a specific feature and key DevOgs engineering activities to be performed during each iteration for the code integration.


D.

The sequence of user stories to be developed in each iteration, along with their start and end timelines, dependencies, and responsible team.


Expert Solution
Questions # 24:

The Agile team has failed to meet their iteration goal, and contention has developed between members. The Agile Leader would like to determine how to improve the team’s productivity and morale.

How should the Agile Leader address this?

Options:

A.

Standup meeting


B.

Retrospective meeting


C.

Demo of the new features to energize the team


D.

Offsite meeting with stakeholders


Expert Solution
Questions # 25:

How should the project team address this issue?

Options:

A.

Suggest pair programming during the retrospective.


B.

Ask the product owner to re-prioritize the user stories at the next retrospective.


C.

Re-estimate the story points with team members at the next iteration planning meeting.


D.

Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.


Expert Solution
Questions # 26:

What should the agile coach tell the team?

Options:

A.

Continuing to track velocity allows functional managers to assess whether or not the team is performing at the desired rate.


B.

The trends will show how the team performs against other Scrum teams in the organization.


C.

Tracking velocity will provide a baseline for the team to see how their continuous improvement efforts are working.


D.

Tracking velocity will document and communicate team health to the stakeholders.


Expert Solution
Questions # 27:

A member of a project ' s development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.

What should the agile team lead do?

Options:

A.

Send the member to training


B.

Ask the outside specialists if database administration is required from the team


C.

Send one member to training only after asking the team if there is an issue with the current workflow


D.

Wait until all members of the team can attend training


Expert Solution
Questions # 28:

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: " I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles. "

What is the agile lead attempting to highlight?

Options:

A.

Ownership, because team members will be in charge of whatever happens during the project life cycle.


B.

Conflict is not productive and team members should resolve issues by themselves.


C.

Better decision-making, because the team is encouraged to join in constructive conflict.


D.

Leaders should incentivize conflict because it is inevitable in the workplace.


Expert Solution
Questions # 29:

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

Options:

A.

Explain to the client that the sprint deadline is approaching and the feature can be included in the next iteration.


B.

Remind the team and the client of the importance of assessing the risks of these features before deciding to include them


C.

Negotiate with the team to add the additional features in this sprint because they are important requirements.


D.

Ask the client for an extension of the deadline to enable delivery of this sprint with the additional features.


Expert Solution
Questions # 30:

While working on a sprint for a software development project, the team is unsure of how the feature should be designed. The project sponsor recommends developing a prototype of the user interface to discover more about this feature.

Why is the project sponsor making this suggestion?

Options:

A.

The information gathered will help the team improve the allocation of resources in developing the most important features.


B.

The project sponsor believes that the agile team is not adding in the most important features during this sprint.


C.

The users can help the team understand if the feature adds value, avoiding the risk of building the wrong product.


D.

The users will start using the software sooner, and the team can start working on the next iteration.


Expert Solution