PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 85 Topic 9 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 85 Topic 9 Discussion

PMI-ACP Exam Topic 9 Question 85 Discussion:
Question #: 85
Topic #: 9

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?


A.

Be transparent with all the stakeholders and make them aware of the issues encountered and the current project's status.


B.

Ensure the agile leader documents a risk in the risk register and communicates the risk to the project sponsor.


C.

Support the team's decision, and since the team is confident about being able to resolve the issues in time, do not raise the issues as risks with the stakeholders.


D.

Ask the product owner to make a decision as to whether or not all the stakeholders should be kept informed about the current project's status.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.