Question #: 86
Topic #: 9

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team ' s productivity.

How should the team leader exhibit servant leadership?


A.

By being a change agent


B.

By being the authority on processes


C.

By being a coach


D.

By removing impediments