A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.
What should the team do to improve its speed of delivery?
A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.
What should the team do to improve its speed of delivery?