PMI-ACP Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.

What should the product owner do?


A.

Terminate the project to cut losses


B.

Review possible options and make an informed decision to cut losses based on delivered business value


C.

Bring in experts to increase the probability of success


D.

Continue the project, release the product without the failing feature, and fix the feature in a subsequent release