PMI-ACP Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?


A.

Help the team to remove impediments that stall project progress.


B.

Work with the development team to adjust the work plan.


C.

Ask the product owner to assign more resources to the project.


D.

Command and control the team to achieve plan goals.