PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 7 Topic 1 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 7 Topic 1 Discussion

PMI-ACP Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?


A.

Focus on performance in the retrospective, then present performance indices and validate with the team.


B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach


C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.