Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 185 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 185 Topic 19 Discussion

CAPM Exam Topic 19 Question 185 Discussion:
Question #: 185
Topic #: 19

The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?


A.

Plan Cost Management


B.

Estimate Activity Resources


C.

Estimate Costs


D.

Determine Budget


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.