PMI Certified Associate in Project Management (CAPM) CAPM Question # 184 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 184 Topic 19 Discussion

CAPM Exam Topic 19 Question 184 Discussion:
Question #: 184
Topic #: 19

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:


A.

budget at completion (BAC)


B.

earned value management (EVM)


C.

to-complete performance index


D.

cost performance index


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.