Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Certified Associate in Project Management (CAPM) CAPM Question # 183 Topic 19 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 183 Topic 19 Discussion

CAPM Exam Topic 19 Question 183 Discussion:
Question #: 183
Topic #: 19

Who should the stakeholders consult to discuss concerns about the current work package?


A.

Project manager


B.

Business analyst


C.

Project coordinator


D.

Project sponsor


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.