CAPM Exam Topic 19 Question 182 Discussion:
Question #: 182
Topic #: 19

The following is a network diagram for a project.

What is the critical path for the project?


A.

A-B-D-G


B.

A-B-E-G


C.

A-C-F-G


D.

A-C-E-G