PMI Certified Associate in Project Management (CAPM) CAPM Question # 156 Topic 16 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 156 Topic 16 Discussion

CAPM Exam Topic 16 Question 156 Discussion:
Question #: 156
Topic #: 16

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?


A.

The project manager should identify and deal with stakeholders only during the execution phase.


B.

Stakeholder satisfaction should be identified immediately and managed as a project objective.


C.

The project manager should focus on project objectives and deal with stakeholders as a secondary priority.


D.

Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.