Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Certified Associate in Project Management (CAPM) CAPM Question # 174 Topic 18 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 174 Topic 18 Discussion

CAPM Exam Topic 18 Question 174 Discussion:
Question #: 174
Topic #: 18

Which of the following are components of the project management plan?


A.

Scope management plan, scope baseline, risk management plan, and configuration managemet plan


B.

Scope management plan, issue log, risk register and project schedule network diagram


C.

Scope management plan, schedule baseline, milestone list, and assumption log


D.

Scope management plan, cost estimates, duration estimates, and resource calenders


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.