PMI Certified Associate in Project Management (CAPM) CAPM Question # 164 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 164 Topic 17 Discussion

CAPM Exam Topic 17 Question 164 Discussion:
Question #: 164
Topic #: 17

A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?


A.

USS-30,000


B.

US$120,000


C.

US$370,000


D.

US$400,000


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.