Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 164 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 164 Topic 17 Discussion

CAPM Exam Topic 17 Question 164 Discussion:
Question #: 164
Topic #: 17

During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?


A.

Move these user stories back to the product backlog for reprioritization.


B.

Remove these user stories as they are not important.


C.

Advance these user stories to the top of the next sprint backlog.


D.

Complete these user stories in the current sprint and extend the sprint length.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.