New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) CAPM Question # 165 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 165 Topic 17 Discussion

CAPM Exam Topic 17 Question 165 Discussion:
Question #: 165
Topic #: 17

A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity's prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

How should the project manager proceed?


A.

Perform Integrated Change Control.


B.

Conduct a risk assessment with the team.


C.

Update the schedule to include compliance.


D.

Manage Stakeholder Engagement.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.