PMI Certified Associate in Project Management (CAPM) CAPM Question # 165 Topic 17 Discussion

PMI Certified Associate in Project Management (CAPM) CAPM Question # 165 Topic 17 Discussion

CAPM Exam Topic 17 Question 165 Discussion:
Question #: 165
Topic #: 17

The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?


A.

Take control of all decisions and product planning.


B.

Build a team that can respond to changes within a collaborative, decision-making environment.


C.

Promote a team with a narrow specialization within a hierarchical environment.


D.

Delegate project decisions to the product owner and sponsor.


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.